List
List
Menu
Home
Exam Simulator
Bus Stop Practice
Questions Blocks
Professional Scrum Master II
Bus Stop Practice
<<
1
2
3
4
5
>>
0%
Question 1 of 5
1.
By the end of the Sprint, a Product Backlog item in the Sprint Backlog does not meet the team’s Definition of Done.
What two things should happen with the item? (Choose two.)
A.
It will be inspected at the Sprint Review and if it is acceptable by the stakeholders then include it in the Increment.
B.
Do not include the item in the Increment for the Sprint.
C.
Split the item and add the estimation of the completed work to the current Sprint so not to impact the velocity and add the ‘undone’ work to the next Sprint.
D.
Estimate the remaining work needed to make it ‘done’ and add it to the Product Backlog for the Product Owner to decide what to do with it.
Question 1 of 5
Question 2 of 5
2.
A Scrum Team has requested a hardening Sprint to integrate the work produced in previous Sprints and test before releasing.
What three scenarios has likely occurred? (Choose three.)
A.
The team's Definition of Done is not being adhered to during every Sprint.
B.
The team's Definition of Done is weak or incomplete causing a build up of technical debt.
C.
The Development Team is having difficulties with the ability to regularly release during a Sprint.
D.
Hardening Sprints are supported by the Scrum framework so this is acceptable.
E.
Scrum has been customized in a suitable manner to make the previous work releasable.
Question 2 of 5
Question 3 of 5
3.
Scrum addresses which of the following four risks in software development? (Choose four.)
A.
The complexity and unpredictability of the requirements.
B.
The stability and complexity of the technology.
C.
The skills and working relationships of the people on the teams.
D.
The timescale of the planned work.
E.
The clear definitions of stages and gateways in the overall governance model.
F.
The definition of incentive and bonus strategies by HR for all team members.
Question 3 of 5
Question 4 of 5
4.
Which statement is correct about the length of the Sprints?
A.
All Sprints must be one month or less and it is optimal to have a consistent Sprint length.
B.
The Sprint length is dependent on the development effort forecasted (amount of items selected) during Sprint Planning.
C.
The Sprint length is calculated by aggregating the time required to design, code and test.
D.
The Sprint Length is defined by the Scrum Master.
Question 4 of 5
Question 5 of 5
5.
Which two scenarios would best represent a self-organizing Development Team? (Choose two.)
A.
The Development Team members are strictly focused on the work within their functional role and always handing off the work to other roles in a timely matter.
B.
Management works with the Scrum Master to optimize the Development Team’s progress during the Sprint.
C.
Development Team members collaboratively select and re-plan their work throughout the Sprint.
D.
The Development Team invites external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog.
E.
The Development Team creates its own Sprint Backlog, reflecting all work that is part of the Definition of Done.
Question 5 of 5
Loading...
Scroll to top
Scroll to top
Scroll to top