4. An agile team uses a burndown chart and a task board to track progress within each iteration. In the burndown chart the X axis represents the days of iteration , the Y axis represents the story points. In the task board the progress of the tasks in the managed via the movement across the following columns:
“To do“, “Ongoing” , “Done“ . A user story for the currnet iteration has associated 20 story points and consists of four tasks T1, T2, T3 and T4. At the end of the fifth day of the next day T1 and T2 move to the "done" column while the T3 an T4 remian in the “Ongoing” column. Based only on the given information.
Which of the following statements would expect most likely to be true at the end of the sixth day of the iteration?