6. Referring the following burndown chart at the end of three weeks----an agile project. The X-axis is used to present the unit of time(days), while the Y-axis is to represent the unit of work (hours) The straight line represent the ideal progress of the iteration from start to finish while the broken line represent actual progress the agile team made during the iteration. Based only on the given information, which of the following statement is true?