CTFL Block18

List List Menú
  • Home
  • Exam Simulator
  • Bus Stop Practice
  • Questions Blocks

Block 18

CTFL – 10 Questions

  • <<
  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • >>
 0%

Question 1 of 10

1. Which of the following BEST describes how using checklist-based testing can result in increased coverage?
A.
B.
C.
D.

Question 1 of 10

Question 2 of 10

2. Which of the following provides the BEST example of a scenario-oriented acceptance criterion?
A.
B.
C.
D.

Question 2 of 10

Question 3 of 10

3. You are using acceptance test-driven development and designing test cases based on the following user story:

As a Regular or Special user, I want to be able to use my electronic floor card, to access specific floors.Acceptance Criteria:AC1: Regular users have access to floors 1 to 3AC2: Floor 4 is only accessible to Special usersAC3: Special users have all the access rights of Regular users

Which test case is the MOST reasonable one to test AC3?
A.
B.
C.
D.

Question 3 of 10

Question 4 of 10

4. Which of the following is NOT a purpose of a test plan?
A.
B.
C.
D.

Question 4 of 10

Question 5 of 10

5.

At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation:

The graph shows the estimated and actual amount of work for the first four iterations.

What is the estimated amount of work for iteration #5?

A.
B.
C.
D.

Question 5 of 10

Question 6 of 10

6.

You are preparing a test execution schedule for executing seven test cases TC 1 to TC 7.
The following figure includes the priorities of these test cases (1=highest priority, 3 = lowest priority).
The figure also shows the dependencies between test cases using arrows. For instance, the arrow from TC 4 to TC 5 means that TC 5 can only be executed if TC 4 was previously executed.

Which test case should be executed sixth?

A.
B.
C.
D.

Question 6 of 10

Question 7 of 10

7. What does the test pyramid model show?
A.
B.
C.
D.

Question 7 of 10

Question 8 of 10

8. What is the relationship between the testing quadrants, test levels and test types?
A.
B.
C.
D.

Question 8 of 10

Question 9 of 10

9. Which of the following is an example of how product risk analysis may influence the thoroughness and scope of testing?
A.
B.
C.
D.

Question 9 of 10

Question 10 of 10

10. Which of the following activities in the test process makes the MOST use of test progress reports?
A.
B.
C.
D.

Question 10 of 10

Loading... Loading...

© Copyright - ISTQB Certification Trainer
Desplazarse hacia arriba Desplazarse hacia arriba Desplazarse hacia arriba