9. You are the Test Manager for a new product developed using an iterative lifecycle. Currently, you have 100% of your smoke tests automated, 20% of your functional tests, and 50% of your regression tests. Each iteration lasts four weeks. Significant maintenance is required for your automated tests in each iteration, causing delays. The test plan mandates that all automated tests be run before any manual tests. Which of the following is a reasonable change to this plan based on the project's progress?